    Budget Warnings

    A project usually has a budget: the person days planned for a work package, or the quantity sold on an order position. decídalo compares the time recorded against each budget and warns the people responsible when it reaches 75% (almost used up) and 100% (used up). The warnings appear in the app wherever the budget is shown, and project contacts can also be told by email.

    Warnings are information only. Recording time on a budget that is used up stays possible, and nothing is blocked.

    Note: Time recording is currently a beta feature. Budget warnings are part of it.

    Which budgets are watched

    Budget Measured in Compared with
    A work package's person days Person days The time recorded on the work package and on all of its sub work packages.
    A time & material order position's sold quantity The position's unit: hours or person days The time recorded on the position, directly or through the work packages connected to it (see Connecting work packages).

    A work package or position without a budget (empty or 0) never warns, and neither does a fixed price position, whose lump sum does not depend on the hours behind it.

    Only time that counts as delivered is compared. Entries that are Suggested (not accepted yet), Cancelled or Cancellation submitted are left out (see the statuses in the Time recording concept). Hours are turned into person days with the daily working hours of your company's default working time pattern, or 8 hours if there is none.

    Level When Shown in
    Budget almost used up 75% of the budget or more is recorded. The warning colour (amber).
    Budget used up 100% of the budget or more is recorded. The error colour (red).

    In the work package drawer

    Open a work package on the project's Work packages tab. Below Recorded days and Remaining days, a bar compares the budget with the time recorded on the work package and its sub work packages, followed by a line such as “12 of 40 PD recorded (30%)”. From 75% the line turns into a warning, for example “Budget almost used up: 31.5 of 40 PD recorded (78%).”, and from 100% into “Budget used up: 44 of 40 PD recorded (110%).” When the budget is exceeded, the bar shows the excess beyond a marker at the budget.

    Recorded days and Remaining days keep counting the work package's own time only; the bar is the one that includes the sub work packages.

    On order positions

    On an order's Positions, the Recorded column of a time & material position shows the recorded time against the sold quantity in the position's unit, for example “176 / 160 h”, with a thin bar below. From 75% a warning icon appears beside it, and pointing at the cell explains it: “Budget used up: 176 of 160 h recorded (110%).” Fixed price positions and positions without a sold quantity show the recorded time alone. See Orders & Positions.

    While recording time

    When you pick a work package as the subject of a new entry in the Record time drawer or in the day view of My Timesheet, a grey hint appears once its budget is almost or fully used up:

    • “The budget of this work package is almost used up (31.5 of 40 PD recorded).”
    • “The budget of this work package is used up (44 of 40 PD recorded). You can still record time.”

    The hint is calculated at the moment you pick the work package, so it is always current. It concerns work packages only: the figures of order positions are billing information and are not shown to the people recording.

    Project warnings

    Where your company uses the Project timeline overview (available as a preview feature), each project's warnings include two budget groups, listed before all others:

    Group Example
    Budget used up “Work package ‘Data migration’: 16.5 of 15 PD recorded (110%).”
    Budget almost used up “Order position ‘Senior developer’ (order PO-2026-114): 124 of 160 h recorded (77%).”

    Each group links to where its budgets are managed: Open work packages for work packages and Open orders (the project's Accounting tab) for order positions. A group holding both kinds shows both links. Budget warnings count towards the number of warnings shown for the project in the overview.

    In the work package view of a project plan, also a preview feature, a work package whose budget is almost or fully used up carries the warning triangle in its row: amber from 75%, red from 100%. Pointing at the triangle shows the same wording as the drawer. The recorded value of the row is tinted in the same colour and has a thin budget bar below it.

    Who sees order position budgets

    Order position budgets reveal what was sold to the customer, so the in-app warnings about them are only shown to people who may see that order's billing data: with Manage accounting, or with Manage project billing and orders on a project they can see. Work package budgets are shown to everyone who can see the project.

    The budget warning email

    The email notification Budget warning for recorded time tells a project's contacts which of its budgets have crossed a threshold. It is off by default; an administrator switches it on and chooses which contact types receive it under Notifications. The Project Manager is preselected.

    • The check runs once a night, so the email reports the state of the previous day, while the app always shows the current state.
    • Each contact gets one email per project, listing every budget that crossed a threshold with its name, budget, recorded time, percentage and a link to the work packages or the order.
    • Each threshold is reported once per budget. A budget that jumps straight past 100% is reported only as used up. It is reported again only after it has fallen below 75%, for example because the budget was raised, and then crossed a threshold anew.
    • Order positions are listed only for recipients who may see the project's billing data, as described above. A recipient without that right gets the work packages only, and no email if only order positions crossed a threshold.
    • Budgets that crossed a threshold while the email was switched off are not reported when it is switched on later.

    See also

    • Orders & Positions: sold quantities and the positions grid.
    • Time recording concept: work packages, order positions and the entry statuses.
    • Notifications: switching the email on and choosing its recipients.